Preliminarna procjena vremena i troškova izgradnje gradskih prometnica primjenom neuronskih mreža
Igor Peško
orcid.org/0000-0001-9098-3642
; University of Novi Sad, Faculty of Technical Sciences, Department of Civil Engineering and Geodesy, Trg Dositeja Obradovica 6, 21000 Novi Sad, Republic of Serbia
Milan Trivunić
; University of Novi Sad, Faculty of Technical Sciences, Department of Civil Engineering and Geodesy, Trg Dositeja Obradovica 6, 21000 Novi Sad, Republic of Serbia
Goran Cirović
orcid.org/0000-0001-7419-8695
; University of Belgrade, Belgrade University College of Applied Studies in Civil Engineering and Geodesy, Department of Civil Engineering, Hajduk Stankova 2, 11000 Belgrade, Republic of Serbia
Vladimir Mučenski
orcid.org/0000-0001-9830-4747
; University of Novi Sad, Faculty of Technical Sciences, Department of Civil Engineering and Geodesy, Trg Dositeja Obradovica 6, 21000 Novi Sad, Republic of Serbia
APA 6th Edition Peško, I., Trivunić, M., Cirović, G. i Mučenski, V. (2013). Preliminarna procjena vremena i troškova izgradnje gradskih prometnica primjenom neuronskih mreža. Tehnički vjesnik, 20 (3), 563-570. Preuzeto s https://hrcak.srce.hr/104086
MLA 8th Edition Peško, Igor, et al. "Preliminarna procjena vremena i troškova izgradnje gradskih prometnica primjenom neuronskih mreža." Tehnički vjesnik, vol. 20, br. 3, 2013, str. 563-570. https://hrcak.srce.hr/104086. Citirano 02.03.2021.
Chicago 17th Edition Peško, Igor, Milan Trivunić, Goran Cirović i Vladimir Mučenski. "Preliminarna procjena vremena i troškova izgradnje gradskih prometnica primjenom neuronskih mreža." Tehnički vjesnik 20, br. 3 (2013): 563-570. https://hrcak.srce.hr/104086
Harvard Peško, I., et al. (2013). 'Preliminarna procjena vremena i troškova izgradnje gradskih prometnica primjenom neuronskih mreža', Tehnički vjesnik, 20(3), str. 563-570. Preuzeto s: https://hrcak.srce.hr/104086 (Datum pristupa: 02.03.2021.)
Vancouver Peško I, Trivunić M, Cirović G, Mučenski V. Preliminarna procjena vremena i troškova izgradnje gradskih prometnica primjenom neuronskih mreža. Tehnički vjesnik [Internet]. 2013 [pristupljeno 02.03.2021.];20(3):563-570. Dostupno na: https://hrcak.srce.hr/104086
IEEE I. Peško, M. Trivunić, G. Cirović i V. Mučenski, "Preliminarna procjena vremena i troškova izgradnje gradskih prometnica primjenom neuronskih mreža", Tehnički vjesnik, vol.20, br. 3, str. 563-570, 2013. [Online]. Dostupno na: https://hrcak.srce.hr/104086. [Citirano: 02.03.2021.]
APA 6th Edition Peško, I., Trivunić, M., Cirović, G. i Mučenski, V. (2013). A preliminary estimate of time and cost in urban road construction using neural networks. Tehnički vjesnik, 20 (3), 563-570. Preuzeto s https://hrcak.srce.hr/104086
MLA 8th Edition Peško, Igor, et al. "A preliminary estimate of time and cost in urban road construction using neural networks." Tehnički vjesnik, vol. 20, br. 3, 2013, str. 563-570. https://hrcak.srce.hr/104086. Citirano 02.03.2021.
Chicago 17th Edition Peško, Igor, Milan Trivunić, Goran Cirović i Vladimir Mučenski. "A preliminary estimate of time and cost in urban road construction using neural networks." Tehnički vjesnik 20, br. 3 (2013): 563-570. https://hrcak.srce.hr/104086
Harvard Peško, I., et al. (2013). 'A preliminary estimate of time and cost in urban road construction using neural networks', Tehnički vjesnik, 20(3), str. 563-570. Preuzeto s: https://hrcak.srce.hr/104086 (Datum pristupa: 02.03.2021.)
Vancouver Peško I, Trivunić M, Cirović G, Mučenski V. A preliminary estimate of time and cost in urban road construction using neural networks. Tehnički vjesnik [Internet]. 2013 [pristupljeno 02.03.2021.];20(3):563-570. Dostupno na: https://hrcak.srce.hr/104086
IEEE I. Peško, M. Trivunić, G. Cirović i V. Mučenski, "A preliminary estimate of time and cost in urban road construction using neural networks", Tehnički vjesnik, vol.20, br. 3, str. 563-570, 2013. [Online]. Dostupno na: https://hrcak.srce.hr/104086. [Citirano: 02.03.2021.]
Sažetak Realizacija projekata u okviru definiranih vremenskih rokova i ugovorenih troškova predstavlja osnovu za uspješno poslovanje izvođačkih građevinskih poduzeća. Odluka pojedinog poduzeća o sudjelovanju u projektu zasniva se prvenstveno na preliminarnoj procjeni potrebnog vremena i troškova za izgradnju projektom definiranog objekta. Investitor navedenu odluku očekuje unutar postavljenog roka uz realnu procjenu kako troškova tako i vremena, pri čemu napori izvođača uloženi u potrebne analize trebaju biti minimalni. Istraživanje provedeno u sklopu ovog rada upućuje da umjetne neuronske mreže (ANN) omogućavaju provođenje opisanih analiza uz zadovoljenje prethodno navedenih kriterija. Odnosno, potvrđeno je da ANN omogućavaju dovoljno točne preliminarne procjene vremena i troškova tijekom izvođenja radova uz minimalno korištenje uobičajeno potrebnih resursa.