Skoči na glavni sadržaj

Ostalo

Elements differentiating the salvage contract from the contract on towage

Vesna Skorupan Wolff orcid id orcid.org/0000-0002-1591-7247 ; Jadranski zavod HAZU, Zagreb, Hrvatska


Puni tekst: hrvatski pdf 221 Kb

str. 109-113

preuzimanja: 377

citiraj


Sažetak

The ship had a halt of the power engine; consequently, the wind and the current pushed
it towards the shore, so that it required the service of towage. The dispute between the
parties arose in relation to whether the concrete case regarded the contract on towage or
the contract on salvage. In this concrete case, the matt er was not of commercial towage,
but rather of salvage.

Ključne riječi

Hrčak ID:

166991

URI

https://hrcak.srce.hr/166991

Datum izdavanja:

27.7.2016.

Podaci na drugim jezicima: hrvatski

Posjeta: 1.085 *