Izvorni znanstveni članak

Access to construction time objectiveness

Mária Kozlovská ; Technical University of Kosice Faculty of Civil Engineering Slovakia
Zuzana Struková ; Technical University of Kosice Faculty of Civil Engineering Slovakia
Alena Tažiková ; Technical University of Kosice Faculty of Civil Engineering Slovakia


Puni tekst: engleski pdf 522 Kb

str. 200-206

preuzimanja: 466

citiraj


Sažetak

One from important requirements of successfully managed building
project is determining of contract parameters (mainly time and
costs) already in project preparation phase. Such consideration
requires a significantly objectified analysis of both influential parameters.
Our research is focused especially to risks resulting from construction
process acceleration. This phenomenon is in construction evident
for several years. The construction processes parameters allow the
time regulation of every operation. For all that the contractor must consider fairly, by what measures and at which “rate” he is able to perform the contract construction time. On the other hand the client must accept objective time possibilities of construction and reconciliation of time parameters between client and contractor must occur.
The paper presents an approach to reconciliation of construction time parameters between client and contractor and affords opportunity to model the trend of contract construction times in various projects segments. The spatial and organizational possibilities of construction process development in individual projects segments determines the measures for performance of construction time similar to contract construction time as more as possible.
Fifty five construction projects were analyzed. Considering the heterogeneousness of their spatial and technological structure, these projects were divided to following segments: multifunctional buildings, shopping centres, production plants and residential buildings. Trends of contract construction time and simulated measures impacts (construction time shortening) were derived for all the segments. The paper presents a possible approach to objectification of building time parameters. The point of the research consists in estimation of expected time limits for intended construction that are necessary for client as well as for forward contractor.

Ključne riječi

construction time performance; construction time shortening; project decision; regression analysis