Tehnički vjesnik, Vol. 24 No. 4, 2017.
Izvorni znanstveni članak
https://doi.org/10.17559/TV-20140612215042
Minimization of direct costs in the construction of torrent control structures
Nada Dragović
orcid.org/0000-0001-8935-0717
; University of Belgrade, Faculty of Forestry, Kneza Višeslava 1, 11 000 Belgrade, Serbia
Tijana Vulević
orcid.org/0000-0003-2417-653X
; University of Belgrade, Faculty of Forestry, Kneza Višeslava 1, 11 000 Belgrade, Serbia
Mirjana Todosijević
; University of Belgrade, Faculty of Forestry, Kneza Višeslava 1, 11 000 Belgrade, Serbia
Stanimir Kostadinov
; University of Belgrade, Faculty of Forestry, Kneza Višeslava 1, 11 000 Belgrade, Serbia
Miodrag Zlatić
; University of Belgrade, Faculty of Forestry, Kneza Višeslava 1, 11 000 Belgrade, Serbia
Sažetak
The most important elements in the planning of the implementation of the torrent (flood) control projects which need to be estimated are time, costs (budget) and resource required. These three elements are interactive: a shorter duration of structure construction causes additional resources engagement and increased costs, and vice versa - greater costs provide a shorter duration of construction. This paper analysis direct project cost minimization for four torrent control projects. The construction duration and the dynamic plan of project activities have been determined using the CPM method of network planning. The optimization problem – minimization of direct cost of construction subject to constraints such as: given deadline, precedence constraints, and upper and lower bounded duration time of activities is solved using linear programming and Matlab toolbox. Our results show that applied methods ensure significant cost savings, which is an important challenge in the construction management.
Ključne riječi
cost minimization; CPM method; linear programming; torrent control
Hrčak ID:
185507
URI
Datum izdavanja:
31.7.2017.
Posjeta: 3.153 *