Skip to the main content

Professional paper

https://doi.org/10.47960/2232-9080.2021.22.11.49

BLASTING TECHNOLOGIES FOR THE EXCAVATION OF THE EVACUATION TUNNEL VRANDUK II ON THE MAIN ROAD M-17

Ekrem Bektašević ; “PPG“ d.o.o. Sarajevo
Hrvoje Antičević ; “PPG“ d.o.o. Sarajevo
Ferid Osmanović ; Federal Administration for Inspection Affairs
Sead Kadrić orcid id orcid.org/0000-0001-6742-966X ; „ZGI“ d.o.o. Mostar
Đenan Žutić ; KPA Unicom Bosnia d.o.o. Sarajevo
Jakov Konta ; West Herzegovina County


Full text: croatian pdf 851 Kb

page 49-60

downloads: 914

cite

Full text: english pdf 834 Kb

page 49-61

downloads: 199

cite


Abstract

The Vranduk II tunnel is located on the main road route of the City of Zenica, on the main road M-17, section Topčić Polje - Lašva 0 with a total length of 1,062 m. A service tube at an axial distance of 25 meters and cross passages from the service tube to the main tunnel tube (three cross passages) were excavated in parallel with the main tunnel tube. The total length of the evacuation tunnel is 856.70 m.
Excavation works were carried out by a combination of blasting and machine excavation. The excavation was performed mainly in sedimentary rocks with the use of wedge and parallel cut. The effect of blasting with the application of wedge cut is much more suitable and appropriate for excavation in a stratified rock mass than blasting with parallel cut.

Keywords

excavation; blasting; sedimentary rock; cut

Hrčak ID:

268151

URI

https://hrcak.srce.hr/268151

Publication date:

22.12.2021.

Article data in other languages: croatian

Visits: 1.962 *