Impact of funding on cost-time aspects of public and social buildings
Ksenija Tijanić
orcid.org/0000-0002-3633-2256
; University of Rijeka, Faculty of Civil Engineering
Diana Car-Pušić
orcid.org/0000-0003-2555-335X
; University of Rijeka, Faculty of Civil Engineering
Ksenija Čulo
orcid.org/0000-0002-1428-4185
; University J.J. Strossmayer in Osijek, Faculty of Civil Engineering Osijek
Sažetak
The comparison of the traditional (budget-funded) public building procurement model with the public private partnership (non-budget funded) model is presented in the paper. Public service buildings procured based on the traditional model and those procured according to the PPP model are compared in the scope of research involving nine buildings realized in the Republic of Croatia. The results point to greater efficiency of the PPP model in the construction of public service buildings, with regard to both cost and time of construction work.
Ključne riječi
traditional procurement model; PPP; public service buildings; costs; construction time