THE TECHNIQUE FOR EXTRAPOLATION OF ROCK MASS INITIAL PARAMETERS DURING THE CONSTRUCTION OF THE TUNNEL
Nemanja Marinković
orcid.org/0000-0001-5834-7910
; Faculty of Civil Engineering and Architecture, University of Niš, Serbia
Milorad Jovanovski
; Faculty of Civil Engineering, “Ss. Cyril and Methodius” University in Skopje, MKD
Elefterija Zlatanović
; Faculty of Civil Engineering and Architecture, University of Niš, Serbia
Lazar Živković
; Faculty of Civil Engineering and Architecture, University of Niš, Serbia
Sažetak
It is important to perform research to the degree that it is adequate to identify the features of the terrain composition, before, during, and after the building of facilities since predicting the behaviour of rock mass during tunnel construction is a complicated engineering challenge. Engineering research works in laboratories and in the field are of different scope and methodology during testing. In this paper, the established interdependencies of some of the basic parameters obtained during the testing of rock mass are presented: Edyn = f(Vp), Edyn = f(RMR) i Edyn = f(Q). Also, the relations between the engineering systems of rock mass classification and seismic primary waves are derived. RMR = f(Vp), Q = f(Vp). The relations were based on the examination of the rock mass for the construction needs of the tunnel on the Nis-Merdare highway. The results obtained in this study can be applied in environments that have similar lithological and structural characteristics.
Ključne riječi
Classification, Extrapolation, Geotechnical model, Physical model, Rock