Assessment of interorganisational conflict in building refurbishment projects using EFA and PLS-SEM

Adel Noori ; School of Architecture and Civil Engineering, Liming Vocational University, Quanzhou, 362046, Fujian, China


Puni tekst: engleski pdf 865 Kb

str. 178-191

preuzimanja: 25

citiraj


Sažetak

It is generally known that building refurbishment (BR) projects are more likely to face uncertainties
than new building projects. Therefore, uncertainty is an
element that may cause interorganisational conflict (IOC).
This paper presents a study with three objectives: to evaluate the uncertainty levels, assess the IOC that may arise
due to the uncertain nature of BR projects and examine
the interrelated dependence relationship between uncertainty and IOC variables. A total of 188 refurbishment pro
jects formed the database for this study. The study applied
Exploratory Factor Analysis (EFA) and Structural Equation
Modelling (SEM) based on Partial Least Squares (PLS) in
the data analysis process. The findings show that uncertainty and IOC BR projects are moderate. Additionally, the
uncertainty variable has a positive relationship with the
IOC variable; in other words, the higher the uncertainty,
the higher is the level of IOC. However, the three factors
that emerged as being predictably more uncertain are
inadequate space for storage of material and working, difficulty in access to the site and unclear scope of the work.

Ključne riječi

interorganisational conflict, building refurbishment projects, uncertainty, structural equation modelling, partial least squares, exploratory factor analysis