Skip to the main content

Preliminary communication

https://doi.org/10.31341/jios.42.2.2

Tracking Predictive Gantt Chart for Proactive Rescheduling in Stochastic Resource Constrained Project Scheduling

Mario Brčić orcid id orcid.org/0000-0002-7564-6805 ; Faculty of Electrical Engineering and Computation University of Zagreb, Zagreb, Croatia
Danijel Mlinarić ; Faculty of Electrical Engineering and Computation University of Zagreb, Zagreb, Croatia


Full text: english pdf 1.088 Kb

page 179-192

downloads: 1.888

cite


Abstract

Proactive-reactive scheduling is important in the situations where the project collaborators need to coordinate their efforts. The coordination is mostly achieved through the combination of the shared baseline schedule and the deviation penalties. In this paper, we present an extension of predictive Gantt chart to the proactive-reactive scheduling needs. It can be used to track the evolution of the relationship between dynamic and static elements through the time. The dynamic elements are evolving probability distributions due to the uncertainty and revealed information. The static elements are time-agreements in the baseline schedule. We demonstrate that in the stateof-the-art proactive-reactive scheduling, the baseline schedule is agnostic to the information received during the project execution. The sources of such inflexibility in the problem model and the scheduling methods are analyzed. The visualization is highlighted as a precursor to developing new methods that proactively change the baseline schedule in accordance with the gained information.

Keywords

Project scheduling; Proactive-reactive scheduling; Gantt chart; Stochastic RCPSP

Hrčak ID:

212208

URI

https://hrcak.srce.hr/212208

Publication date:

10.12.2018.

Visits: 4.495 *