Risk Assessment of Wave Energy Converter At Kuantan Port, Pahang

Muhammad Asyraf Abdullah orcid id orcid.org/0000-0002-7851-6790 ; National Defence University of Malaysia, Faculty of Engineering
Noh Zainal Abidin ; National Defense University of Malaysia, Faculty of Science and Defense Technology
Zulkifly Mat Radzi ; National Defense University of Malaysia, Faculty of Science and Defense Technology
Mohd Arif Ahmad ; National Defense University of Malaysia, Faculty of Science and Defense Technology
Vikneswaran Munikanan ; National Defence University of Malaysia, Faculty of Engineering
Mohd Norsyarizad Razali ; National Defense University of Malaysia, Faculty of Science and Defense Technology
Neza Ismail ; National Defence University of Malaysia, Faculty of Engineering


Full text: english pdf 163 Kb

page 318-329

downloads: 268

cite


Abstract

Harvesting energy from ocean waves remains an untapped resource, and it is considered a new methodology in renewable energy, especially in Malaysia. This research is based on a project at Kuantan Port that used Wave Energy Converter (WEC) as a platform to generate energy from waves and convert it into electricity. The purpose of this research is to conduct a risk assessment before the execution of the project by referring to the International Organization for Standardization (ISO) 31000 and Risk Management Guidelines: Companion to AS/NZS 4360:2004. It started from risk identification and planned a mitigation way to reduce the grade of risk. These mitigations will be monitored throughout the project to avoid any accidents or harm during construction and installation in the future. The assessment will be using a qualitative analysis method that will gather all the possible risks that impact the project and propose the actions to mitigate the risk. The assessment will also consider the likelihood, seriousness, and weightage to determine the risk level. The risk assessment is divided into six clusters: project management, hydrography, mechanical, electrical, civil, and safety and security. After analysis, each cluster has given their feedback on the risk assessment and their cluster-s risk grade. This research has found that the risk grade is at grade C, which needs the risk assessment of this project to reduce the likelihood, seriousness, and required mitigation actions. Eventually, after the mitigation plan is applied to each risk, the grade of risk is reduced to N.

Keywords

Renewable energy; Wave energy converter; Risk assessment; Risk mitigation; Qualitative analysis