Skip to the main content

Original scientific paper

https://doi.org/10.5592/otmcj.2012.1.9

Scope Control Through Managing Changes in Construction Projects

Maja-Marija Nahod orcid id orcid.org/0000-0002-1785-3128 ; University of Zagreb, Faculty of Civil Engineering


Full text: english pdf 839 Kb

page 438-447

downloads: 7.004

cite


Abstract

Projects need to be performed and delivered under certain constraints. Traditionally, these constraints are scope, time and cost. The Scope Control process influences the factors that lead to project scope changes and control the impact of those changes, which a key issue for project success. It ensures that all requested changes and recommended corrective actions are processed and that changes are reduced or eliminated if they result in negative impact on projects. The scope control is considered from the investor’s point of view, as achieving the project goals is of primary importance for the investor. The theoretical basis for the research is Dynamic Planning and Control Methodology (“DPM”). Practical implications and adjustments are obtained, to result in an efficient system for managing changes throughout a project. Research was conducted through questionnaire and interviews. Findings include reasons for and consequences of changes from the point of view of various stakeholders in the project, as well as recommended procedures for objective and practical management of the changes. The study discusses the basic constraints:
cost and time. Further research should focus on quantifying and determining the quality impact of changes and impact of the project manager’s competencies on managing changes. The recommended
procedures are applicable for any building construction project, but specific goals and constraints have to be incorporated into the calculation. Furthermore, a database of projects and changes could be created to facilitate preliminary assessments of the impact of changes on future projects.

Keywords

Managing changes; Building Construction Projects; Project Change; Dynamic Planning

Hrčak ID:

83813

URI

https://hrcak.srce.hr/83813

Publication date:

1.6.2012.

Visits: 9.371 *