Original scientific paper
https://doi.org/10.1515/otmcj-2016-0028
An integration of spreadsheet and project management software for cost optimal time scheduling in construction
Tadej Valenko
; University of Maribor, Faculty of Civil Engineering, Transportation Engineering and Architecture, Smetanova ulica 17, 2000 Maribor, Slovenia
Uroš Klanšek
orcid.org/0000-0002-7341-8761
; University of Maribor, Faculty of Civil Engineering, Transportation Engineering and Architecture, Smetanova ulica 17, 2000 Maribor, Slovenia
Abstract
Successful performance and completion of
construction projects highly depend on an adequate
time scheduling of the project activities. On implementation
of time scheduling, the execution modes of activities
are most often required to be set in a manner that
enables in achieving the minimum total project cost.
This paper presents an approach to cost optimal time
scheduling, which integrates a spreadsheet application
and data transfer to project management software
(PMS). At this point, the optimization problem of project
time scheduling is modelled employing Microsoft Excel
and solved to optimality using Solver while organization
of data is dealt by macros. Thereupon, Microsoft Project
software is utilized for further managing and presentation
of optimized time scheduling solution. In this way,
the data flow between programs is automated and possibilities
of error occurrence during scheduling process
are reduced to a minimum. Moreover, integration of
spreadsheet and PMS for cost optimal time scheduling
in construction is performed within well-known
program environment that increases the possibilities
of its wider use in practice. An application example is
shown in this paper to demonstrate the advantages of
proposed approach.
Keywords
optimization; project scheduling; spreadsheet application; project management software
Hrčak ID:
198173
URI
Publication date:
30.1.2017.
Visits: 2.717 *