Technical gazette, Vol. 26 No. 2, 2019.
Original scientific paper
https://doi.org/10.17559/TV-20180410114808
Minimizing the Pessimistic Time of Activity in Overhaul Project
Josip Jukić
; College of Slavonski Brod, Dr. Mile Budaka 1, 35000 Slavonski Brod, Croatia
Roberto Lujić
orcid.org/0000-0001-5123-3064
; Josip Juraj Strossmayer University of Osijek, Mechanical Engineering Faculty in Slavonski Brod, Trg Ivane Brlić Mažuranić 2, 35000 Slavonski Brod, Croatia
Dražen Barković
; Josip Juraj Strossmayer University of Osijek, Faculty of Economics in Osijek, Trg Ljudevita Gaja 7, 31000 Osijek, Croatia
Abstract
The objective of this paper is to analyse some concepts of the project management techniques and the proposed mathematical model for estimating the project completion probability after crashing of PERT/CPM network. The main objective is to minimize the pessimistic time of the activity, which lies on the critical path by investing additional amounts of money to the project. The increment of the investment not only decreases the pessimistic time of the activities along the critical path, but it also decreases the expected time of activities along the critical path of the whole project duration.
Keywords
CPM; crashing time; PERT; project management
Hrčak ID:
219526
URI
Publication date:
24.4.2019.
Visits: 2.062 *