Technical gazette, Vol. 26 No. 2, 2019.
Original scientific paper
https://doi.org/10.17559/TV-20180618102041
Risk Management of a Hydro Power Plant – Fracture Mechanics Approach
Ivana Vučetić
; Innovation center of the Faculty of Mechanical Engineering, Kraljice Marje 16, 11020 Belgrade 35, Serbia
Snežana Kirin
; Innovation Ccenter of the Faculty of Mechanical Engineering, Kraljice Marije 16, 11020 Belgrade 35, Serbia
Aleksandar Sedmak
orcid.org/0000-0002-5438-1895
; University of Belgrade, Faculty of Mechanical Engineering, Kraljice Marije 16, 11020 Belgrade 35, Serbia
Tamara Golubović
; University of Belgrade, Faculty of Mechanical Engineering, Kraljice Marije 16, 11020 Belgrade 35, Serbia
Mirjana Lazić
; University of Kragujevac, Faculty of Sciences, Department of Mathematics and Informatics, Radoja Domanovića 12, 34000 Kragujevac, Serbia
Abstract
Risk management of a hydro power plant has been analysed from fracture mechanics point of view. The research is focused on the risk and integrity assessment of pressure equipment in a reversible hydro power plant in order to determine to what extent it poses a risk to Bajina Basta settlement and its inhabitants. The risk matrix has been used to assess risk level according to probability and consequence in a more descriptive way, whereas the failure assessment diagram has been used as an alternative engineering approach, including level II analysis.
Keywords
pressure vessel; reversible hydro power plant; risk management; settlement
Hrčak ID:
219532
URI
Publication date:
24.4.2019.
Visits: 2.192 *