Sažetak

The ship had a halt of the power engine; consequently, the wind and the current pushed
it towards the shore, so that it required the service of towage. The dispute between the
parties arose in relation to whether the concrete case regarded the contract on towage or
the contract on salvage. In this concrete case, the matt er was not of commercial towage,
but rather of salvage.