Skip to the main content

Original scientific paper

Ensuring Electromagnetic Compatibility in Nuclear Power Plant beyond Equipment Qualification Tests

Hrvoje Grganić ; Nuclear Power Plant Krško Vrbina 12, 8270, Krško
Marko Valjak ; Nuclear Power Plant Krško Vrbina 12, 8270, Krško
Gregor Škorc ; Nuclear Power Plant Krško Vrbina 12, 8270, Krško
Luka Romac ; Nuclear Power Plant Krško Vrbina 12, 8270, Krško


Full text: english pdf 1.191 Kb

downloads: 283

cite


Abstract

Electromagnetic compatibility (EMC) is defined as the capability of equipment or system to
function satisfactorily in its electromagnetic environment without introducing intolerable
electromagnetic disturbances to anything in that same environment [1]. EMC regulatory
requirements for instrumentation and control (I&C) equipment were not developed or in effect until
the last few years. Therefore, there is a considerable number of plant equipment that has not been
qualified for EMC. The current EMC regulatory requirements address new and modified equipment
only, and do not call for testing of existing equipment. There is a gap, which has to be overcome, in
order to understand the current level of EMC within the plant.
Equipment qualification normally implies formal tests in EMC chambers, which is not
practical for the equipment already installed. This paper is a short overview of the preparation phase
of a project that includes various EMC-related activities currently being performed in Krško nuclear
power plant (NPP). The activities are categorized into two main groups: equipment immunity
(susceptibility) tests, used as an assessment of the immunity of the existing equipment such as
process cabinets, transmitters and similar, and zone mapping measurements, which are performed to
record the electromagnetic environment of the selected plant areas.
There is no clear, detailed and unambiguous guidance on how to perform any of these tests. It
takes a lot of engineering judgement to optimize them for a specific plant. Some of the most
important questions addressed in this paper are 1) the selection of the plant areas for zone mapping
measurements and susceptible equipment to be tested for immunity, 2) choice of electromagnetic
disturbances, which shall be simulated during those tests, and 3) practical performance, i.e.
harmonization of immunity tests with operation of other plant systems. It is necessary to decide
which operation mode poses the “worst-case”, i.e. how and when the immunity tests and zone
mapping measurement should be performed.
The paper also addresses troubleshooting of poor EMC design and installation practices,
which can significantly reduce the number of EMC-related problems in a plant.

Keywords

electromagnetic compatibility, electromagnetic interference, equipment testing, site surveys, in-situ tests

Hrčak ID:

247088

URI

https://hrcak.srce.hr/247088

Publication date:

28.10.2019.

Visits: 731 *