Pressure Control Technology at the Hard Thick Sandstone Roof in an Island Mining Face with a Large Mining Height

Baojie Fu* ; Key Laboratory of Mining Coal Safety and Efficiently Constructed by Anhui Province and Ministry of Education, Anhui University of Science and Technology, Huainan, China; Sch. of Mining & Safety, Anhui University of Science and Technology, Huainan, China
Min Tu ; Key Laboratory of Mining Coal Safety and Efficiently Constructed by Anhui Province and Ministry of Education, Anhui University of Science and Technology, Huainan, China; Sch. of Mining & Safety, Anhui University of Science and Technology, Huainan, China
Qingchong Zhao ; Sch. of Mining & Safety, Anhui University of Science and Technology, Huainan, China, 232001, No.168 Taifeng Street, Huainan, Anhui Province


Puni tekst: engleski pdf 2.156 Kb

str. 1863-1869

preuzimanja: 611

citiraj


Sažetak

Fracture of a critical stratum on a coal seam roof may cause strong strata pressure behaviours. In particular, a large-scale sudden fracture of the critical stratum, which is formed by hard thick sandstones on a mining face with a large mining height, can easily cause dynamic disasters of wells. In this study, a simulation analysis of the deformation and failure laws of a hard thick roof in an island mining face with a large mining height in Xinji 2# Mine 210106 after the mining of Coal bed A1 was performed in accordance with the occurrence characteristics of sandstones. Results demonstrate that large-scale fracture suddenly occurs at a gob roof after the working face is advanced by 120 m. A mechanical analysis model of the island working face was constructed. This model comprises 17.9 m of fracture on the 16 m thick sandstone roof. Hydraulic support provides 16854.1 kN of supporting resistance to maintain the stability of the rock beam and thus prevent threats to the supporting devices of the working face. The hard thick roof was weakened every 15 m in the transport gateway and air return in advance through an advanced deep-hole pre-splitting blasting technique. In accordance with the measurement results of underground pressure, the forced caving of thick sandstones relieves the influence of roof loads on the support and thus realizes safe mining.

Ključne riječi

critical hard thick stratum; large mining height; pre-splitting blasting; roof control