hrcak mascot   Srce   HID

Ostalo

Carriage of goods by sea - Determination of a place for discharge of the goods and expenses connected with the discharge operations : [case review]

Andrija Eraković ; Zagreb, Hrvatska

Puni tekst: hrvatski, pdf (583 KB) str. 147-152 preuzimanja: 56* citiraj
APA 6th Edition
Eraković, A. (1991). Prijevoz stvari morem - određivanje mjesta iskrcaja tereta i snašanje troškova iskrcaja : [prikaz presude]. Uporedno pomorsko pravo, 33 (129-130), 147-152. Preuzeto s https://hrcak.srce.hr/212400
MLA 8th Edition
Eraković, Andrija. "Prijevoz stvari morem - određivanje mjesta iskrcaja tereta i snašanje troškova iskrcaja : [prikaz presude]." Uporedno pomorsko pravo, vol. 33, br. 129-130, 1991, str. 147-152. https://hrcak.srce.hr/212400. Citirano 12.04.2021.
Chicago 17th Edition
Eraković, Andrija. "Prijevoz stvari morem - određivanje mjesta iskrcaja tereta i snašanje troškova iskrcaja : [prikaz presude]." Uporedno pomorsko pravo 33, br. 129-130 (1991): 147-152. https://hrcak.srce.hr/212400
Harvard
Eraković, A. (1991). 'Prijevoz stvari morem - određivanje mjesta iskrcaja tereta i snašanje troškova iskrcaja : [prikaz presude]', Uporedno pomorsko pravo, 33(129-130), str. 147-152. Preuzeto s: https://hrcak.srce.hr/212400 (Datum pristupa: 12.04.2021.)
Vancouver
Eraković A. Prijevoz stvari morem - određivanje mjesta iskrcaja tereta i snašanje troškova iskrcaja : [prikaz presude]. Uporedno pomorsko pravo [Internet]. 1991 [pristupljeno 12.04.2021.];33(129-130):147-152. Dostupno na: https://hrcak.srce.hr/212400
IEEE
A. Eraković, "Prijevoz stvari morem - određivanje mjesta iskrcaja tereta i snašanje troškova iskrcaja : [prikaz presude]", Uporedno pomorsko pravo, vol.33, br. 129-130, str. 147-152, 1991. [Online]. Dostupno na: https://hrcak.srce.hr/212400. [Citirano: 12.04.2021.]

Sažetak
If the place for discharge of goods is clearly identified in a contract for carriage of goods by sea, it will be considered that the charterer neither had knowledge nor ought to have had knowledge of the vessels's characteristics relavant for the piering at the designated place. Therefore it is for the charterer to bear the consequences arising out of any impossibility for the vessel to berth at the contracted place even if the operator failed to give notice thereof to the charterer. It must be considered that the vessel arrived on time if she was ready for discharge of cargo at the agreed or usual time. If the vessel was not ready for discharge of the cargo, any waiting for working power does not represent a delay in discharging of such cargo.

Ključne riječi
case review; carriage of goods by sea; discharge of goods - place; discharge of goods - expenses; contract for carriage of goods;

Hrčak ID: 212400

URI
https://hrcak.srce.hr/212400

[hrvatski]

Posjeta: 109 *